Meta is reportedly in talks with JERA, Japan’s largest electricity producer, about building AI data centers next to power plants in the Tokyo area. The behind-the-meter approach could give Meta a direct, stable power source and help it avoid potential grid-connection delays of up to a decade in the region.

Meta’s capital expenditure guidance for 2026 is $135 billion to $145 billion. A large portion is dedicated to AI infrastructure.

Meta shares climbed more than 3% in midday trading after the news. The discussions also reportedly involve other major technology companies, as firms compete for secure energy supplies to support power-intensive AI data centers.