Soluna Holdings announced that its subsidiary has entered into a co-mining agreement with a subsidiary of Bitdeer Technologies Group (NASDAQ: BTDR). Under the agreement, Bitdeer will deploy 28 MW of Bitcoin mining equipment, adding approximately 1.93 EH/s of hash rate at Soluna’s Project Kati 1 facility in South Texas.

Key Details

  • Agreement Structure: This is a co-mining arrangement where Soluna provides the site, power, and operations, while Bitdeer provides and owns its mining equipment. Both parties will share the mining proceeds.
  • Deployment Details: The agreement covers approximately 28 MW of equipment, expected to contribute 1.93 EH/s of hash rate, with deployment beginning in September 2026.
  • Location: The deployment will take place at Project Kati 1, Soluna's 83 MW wind-powered data center in Willacy County, Texas.